After many months of hard work, the new £1 million waste water treatment plant is now open and operating.

Colchester Construction Services Ltd undertook the full civil engineering package including:

  • Cut & fill works.
  • New drainage installation.
  • Drainage diversions to accomodate the new plant.
  • Construction of concrete bases.
  • Groundworks to new plant house.
  • Construction of new concrete service yard.

All works were undertaken within a live industrial factory and many interfaces between the client and the works were required.