Construction of new R/C building

We have been engaged to undertake the construction of a new reinforced concrete house.

Our works package includes:

  • Demolition of existing property.
  • Installation of drainage.
  • Sheet piling.
  • Cut / fill of existing site.
  • Reinforced concrete floor slab, walls and soffit slab.

The works are less than 500m from the sea and the works relating to the reduced level excavation are highly dependant on the tides.

There has also been a requirement to sheet pile the perimeter of the site to prevent movement of the sands and gravels on site.