Mercury Theatre, Colchester

We have secured a project which is due to commence in March 2019 for the construction of an extension to the existing theatre. Our works will consist of reduced level excavation working alongside the Archaeological Team, installation of piling mat with piling attendance, excavation of new reinforced pad and ground beam foundation and construction of the new reinforced ground floor slab. Following the completion of the building phase 2 will consist external drainage, new services duct with a new sub-station and external works to the existing footpath and highway.

UPDATE

We have successfully completed phase 1 of the project and are currently undertaking the works to
phase 2, with an anticipated completion in Spring 2020.